Case study · Commercial Property

Complex LV Switchgear Fault Investigation

Central London Commercial Building

Specialist investigation of phase loss within a commercial LV distribution system, combining measured testing, safe isolation and detailed inspection to localise the fault evidence.

Commercial Electrical Fault-FindingLV DistributionSwitchgear InvestigationElectrical Testing
Commercial LV switchboard investigated following a partial power failure
Existing LV switchboard investigated following loss of two phases to downstream circuits.

Project context

Site
Central London Commercial Building
Sector
Commercial Property
Location
Central London

The challenge

Partial power loss after the main supply was restored.

Following a major supply failure affecting part of the landlord's commercial distribution system, the main supply was reinstated but several circuits remained without power. Testing at the reception distribution board confirmed that phases L1 and L3 were absent.

The fault therefore had to be traced upstream through the LV distribution arrangement, with the affected equipment isolated and the condition of the downstream installation established before remedial decisions were made.

Initial diagnosis

Incoming supply present. Two outgoing phases absent.

Testing at the upstream 250 A switch-disconnector confirmed all three phases on the incoming side, but only one phase on the outgoing side. Internal damage, arcing evidence and debris were identified within the device.

The switch-disconnector was treated as unsafe and isolated. A controlled temporary alternative supply arrangement was established to maintain reception services while the investigation and remedial process continued, with the existing protective arrangements retained.

Open damaged 250 amp switch-disconnector examined during LV fault investigation
Internal damage identified within the 250 A switch-disconnector.

Measured testing

Test the downstream circuit before assuming the failed device was the cause.

With the damaged equipment removed and the downstream sub-main confirmed dead, insulation-resistance testing returned readings greater than 999 MΩ. The satisfactory result helped narrow the investigation away from the downstream cable and connected distribution board.

This distinction was important: the visibly failed switch-disconnector was consequentially damaged equipment, but it did not by itself establish where the fault evidence originated.

Megger instrument displaying greater than 999 megohms during sub-main insulation-resistance testing
Insulation-resistance testing of the isolated downstream sub-main returned greater than 999 MΩ.

Root-cause localisation

The investigation continued beyond the component that had failed.

Inspection of the switchboard and connected equipment found arcing and burnt-metal residue around the fire-alarm-panel isolator connected to the incomer busbar. The isolator was removed and the remaining busbar assembly returned insulation-resistance readings greater than 100 MΩ.

The measured evidence localised the fault to the fire-alarm isolator and incomer-busbar area. The precise initiating object or mechanism could not be verified because the intensity of the arc had destroyed or disintegrated the relevant evidence, so no unsupported cause was assigned.

Arc residue visible within an LV switchboard compartment during detailed inspection
Localised arc residue inspected after removal of the damaged equipment.

Investigation evidence

Inspection and verification within the existing switchboard.

Internal busbar and cable compartment inspected during LV switchgear fault-finding
Internal switchboard inspection used to follow the distribution path and localise fault evidence.
Insulation-resistance verification of an isolated LV busbar assembly
Verification testing of the isolated busbar assembly following equipment removal.

Engineering capability

Evidence-led investigation across LV distribution and switchgear.

LV switchgear fault-finding

Commercial distribution systems

250 A switch-disconnector investigation

Phase-loss diagnosis

Sub-main insulation-resistance testing

Busbar inspection and verification

Arc-fault evidence localisation

Safe isolation and continuity planning

Evidence-led root-cause investigation

Photographic technical reporting

Outcome

From phase loss to a defensible fault location.

The investigation separated the failed switch-disconnector from the area in which the fault evidence originated. Systematic testing verified the downstream sub-main, while progressive inspection and further insulation-resistance testing localised the evidence to the fire-alarm isolator and incomer-busbar area.

This provided a technically supported basis for the next remedial steps without presenting an unverified initiating cause as fact.

Fault-finding is not simply replacing the component that failed. It is understanding why it failed.